The environmental impact assessment has been approved
A construction permit has already been issued
Expected Completion Date Mid-december 2013
Overall construction work completed 29%
| |
Pecentage Completed |
Work has progressed up to |
| 1. Structural Work |
44% |
7th floor |
| 2. Systems installation |
- |
- |
| 3. Architectural Work |
- |
- |