The environmental impact assessment has been approved
A construction permit has already been issued
Expected Completion Date : mid November 2012
Overall construction work completed 55%
| |
Pecentage Completed |
Work has progressed up to |
| 1. Structural Work |
70% |
18th floor |
| 2. Systems installation |
25% |
11th floor |
| 3. Architectural Work |
10% |
11th floor |