The environmental impact assessment has been approved
A construction permit has already been issued
Expected Completion Date : November 2012
Overall construction work completed 70%
| |
Pecentage Completed |
Work has progressed up to |
| 1. Structural Work |
83% |
25th floor |
| 2. Systems installation |
48% |
18th floor |
| 3. Architectural Work |
32% |
17th floor |