The environmental impact assessment has been approved
A construction permit has already been issued
Expected Completion Date : November 2012
Overall construction work completed 75%
| |
Pecentage Completed |
Work has progressed up to |
| 1. Structural Work |
90% |
28th floor |
| 2. Systems installation |
58% |
22th floor |
| 3. Architectural Work |
43% |
19th floor |