dcondo Ramkhamhaeng
Construction update August 2011

The environmental impact assessment has been approved 
A construction permit has already been issued
 
Expected Completion Date March 2012
Overall construction work completed 51%

 



  Pecentage Completed Work has progressed up to
1. Structural Work 97% 8 th floor
2. Systems installation 38% 4 th floor
3. Architectural Work 24% 3 th floor