Chelona Khaotao
Construction update May 2012

The environmental impact assessment has been approved 
A construction permit has already been issued
 
Expected Completion Date : December 2012
Overall construction work completed 50%



 

 

  Pecentage Completed Work has progressed up to
1. Structural Work 93% Structural Work completed on Building 5
2. Systems installation 33% Building 1 and 3
3. Architectural Work 28% Plastering of Buildings 1, 2 and 3

 