Construction update October 2011
An environmental impact assessment approval has been granted
The building permit has been issued
Expected Completion Date February 2013
Overall construction work completed 49%
| |
Pecentage Completed |
Work has progressed up to |
| 1. Structural Work |
80% |
28th floor |
| 2. Systems installation |
37% |
18th floor |
| 3. Architectural Work |
30% |
17th floor |