Construction update December 2011
An environmental impact assessment approval has been granted
The building permit has been issued
Expected Completion Date February 2013
Overall construction work completed 64%
| |
Pecentage Completed |
Work has progressed up to |
| 1. Structural Work |
87% |
Roof Terrace |
| 2. Systems installation |
54% |
28th floor |
| 3. Architectural Work |
51% |
27th floor |