The Standard Residences Hua Hin
100%
Completion date: September 2026
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
Structural work
100%
- Pile-driving work is completed 100%
- Tower A:Structual work is finished up to 7 th floor
- Tower B:Structual work is finished up to basement
- Tower B:Structual work is finished up to 4 th floor
- Tower B:Structual work is finished up to 4 th floor
- Tower B:Structual work is finished up to 4 th floor
- Tower B:Structual work is finished up to 4 th floor
- Tower B:Structual work is finished up to 4 th floor
- Tower B:Structual work is finished up to 4 th floor
- Tower B:Structual work is finished up to 4 th floor
System installation
100%
- Tower A: Eletrical systems are finished up to 8 th fl., pumbling systems on 8 th fl. A/C systems on 8 th fl.
- Tower B: Eletrical systems are finished up to 1st fl. pumbling systems on 1 st fl. A/C systems on 1 st fl
- Tower C:Eletrical systems are finished up to 4th fl. pumbling systems on 4th fl. A/C systems on 4th fl
- Tower D: Eletrical systems are finished up to 4th fl. , pumbling systems on 4th fl. A/C systems on 4th fl.
- Tower E: Eletrical systems are finished up to 4th fl. pumbling systems on 4th fl. A/C systems on 4th fl.
- Tower F: Eletrical systems are finished up to 4th fl, pumbling systems on 4th fl. A/C systems on 4th fl.
- Tower G: Eletrical systems are finished up to 4th fl. pumbling systems on 4th fl.A/C systems on 4th fl.
- Tower :H Eletrical systems are finished up to 4th floor, pumbling systems on 4th fl. A/C systems on 4th fl.
- Tower I: Eletrical systems are finished up to 4th floor, pumbling systems on 4th fl. A/C systems on 4th fl.
Architecture
100%
- Tower A : Wall construction is finished up to 8 th floor
- Tower B : Wall construction is finished up to 1 st floor
- Tower C : Wall construction is finished up to 4th floor
- Tower D : Wall construction is finished up to 4th floor
- Tower E : Wall construction is finished up to 4th floor
- Tower F : Wall construction is finished up to 4th floor
- Tower G : Wall construction is finished up to 4th floor
- Tower H : Wall construction is finished up to 4th floor
- Tower I : Wall construction is finished up to 4th floor
- '''In progress of QC End Product