The Standard Residences Hua Hin

100%

Completion date: September 2026

  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.

Structural work

100%
  • Pile-driving work is completed 100%
  • Tower A:Structual work is finished up to 7 th floor
  • Tower B:Structual work is finished up to basement
  • Tower B:Structual work is finished up to 4 th floor
  • Tower B:Structual work is finished up to 4 th floor
  • Tower B:Structual work is finished up to 4 th floor
  • Tower B:Structual work is finished up to 4 th floor
  • Tower B:Structual work is finished up to 4 th floor
  • Tower B:Structual work is finished up to 4 th floor
  • Tower B:Structual work is finished up to 4 th floor

System installation

100%
  • Tower A: Eletrical systems are finished up to 8 th fl., pumbling systems on 8 th fl. A/C systems on 8 th fl.
  • Tower B: Eletrical systems are finished up to 1st fl. pumbling systems on 1 st fl. A/C systems on 1 st fl
  • Tower C:Eletrical systems are finished up to 4th fl. pumbling systems on 4th fl. A/C systems on 4th fl
  • Tower D: Eletrical systems are finished up to 4th fl. , pumbling systems on 4th fl. A/C systems on 4th fl.
  • Tower E: Eletrical systems are finished up to 4th fl. pumbling systems on 4th fl. A/C systems on 4th fl.
  • Tower F: Eletrical systems are finished up to 4th fl, pumbling systems on 4th fl. A/C systems on 4th fl.
  • Tower G: Eletrical systems are finished up to 4th fl. pumbling systems on 4th fl.A/C systems on 4th fl.
  • Tower :H Eletrical systems are finished up to 4th floor, pumbling systems on 4th fl. A/C systems on 4th fl.
  • Tower I: Eletrical systems are finished up to 4th floor, pumbling systems on 4th fl. A/C systems on 4th fl.

Architecture

100%
  • Tower A : Wall construction is finished up to 8 th floor
  • Tower B : Wall construction is finished up to 1 st floor
  • Tower C : Wall construction is finished up to 4th floor
  • Tower D : Wall construction is finished up to 4th floor
  • Tower E : Wall construction is finished up to 4th floor
  • Tower F : Wall construction is finished up to 4th floor
  • Tower G : Wall construction is finished up to 4th floor
  • Tower H : Wall construction is finished up to 4th floor
  • Tower I : Wall construction is finished up to 4th floor
  • '''In progress of QC End Product