THE BASE Wongsawang

72%

Expected completion date: June 2027

  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.

Structural work

94%
  • Pile-driving work is completed 100%
  • Structual work is finished up to 39th floor

System installation

71%
  • Installations of eletrical systems are finished up to 7 th floor, pumbling systems on 7 th floor and A/C systems on 7th floor

Architecture

53%
  • ' Wall construction is finished up to 31 th floor