PTY Residence Sai 1

73%

Expected completion date: May 2027

  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.

Structural work

99%
  • Pile-driving work is completed 100%
  • Structual work is finished up to 27th floor

System installation

64%
  • Installations of eletrical systems are finished up to 24 th floor, pumbling systems on 23 rd floor and A/C systems on 22th floor

Architecture

52%
  • Wall construction is finished up to 25 th floor
Visit project website