valles HAUS

88%

Expected completion date: December 2026

  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.

Structural work

100%
  • Pile-driving work is completed 100%
  • Tower A:Structual work is finished up to 7 th floor
  • Tower B:Structual work is finished up to 7 Floor
  • Tower C:Structual work is finished up to 7 floor
  • Tower D:Structual work is finished up to 2 nd floor

System installation

85%
  • Tower A: Installations of eletrical systems are finished up to 7th floor
  • Tower A: Pumbling systems on 7 th floor
  • Tower A:A/C system up to 7 th floor
  • Tower B : Eletric system up to 7th floor
  • Tower B: Pumbling systems on 7 th floor
  • Tower B: A/C system are finished up to 7th floor
  • Tower C: Eletrical system are finished up to 7 th floor
  • Tower C: Pumbling system on 7 th floor
  • Tower C: A/C system up to 7 floor

Architecture

80%
  • Tower A'Wall construction is finished up to 7 th floor
  • Tower B'Wall construction is finished up to 7 th floor
  • Tower C'Wall construction is finished up to 7 th floor
  • '''In progress of QC End Product