dcondo cove Phuket

41%

Expected completion date: September 2027

  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.

Structural work

77%
  • Pile-driving work is completed 100%
  • Tower A:Structual work is finished up to 7 th floor
  • Tower B:Structual work is finished up to 8 th floor
  • Tower C:Structual work is finished up to 8 th floor
  • Tower D:Structual work is finished up to 6th floor

System installation

29%
  • Tower A:Eletric work is finished up to 4 th floor
  • Tower A:Pumbling work is finished up to 4 th floor
  • Tower A: A/C work is finished up to
  • Tower B:Eletric work is finished up to 5 th floor
  • Tower B: Pumbling work is finished up to 5 th floor
  • Tower B:A /C work is finished up to
  • Tower C:Eletric work is finished up to 5 th floor
  • Tower C:Pumbling work is finished up to 5 th floor
  • Tower C:A / C work is finished up to
  • Tower D:eletric work is finished up to 3 rd floor
  • Tower D:Pumbling work is finished up to 3 rd floor

Architecture

19%
  • Tower B: Wall construction is finished is 3 rd floor
  • Tower C: Wall construction is finished is 5 th floor