LOVE Charoen Nakhon

15%

Expected completion date: February 2029

  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.

Structural work

39%
  • Pile-driving work is completed 83%

System installation

0%

Architecture

0%
Visit project website