THE LINE Ratchathewi
Expected completion Date:April 2018
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Structural flooring work has finished up to Floor 20
-
Systems installation
Installation of systems completed on Floor 20
-
Architectural Work
Brick-laying and plastering work has completed up to Floor 16