THE LINE Asoke-Ratchada
Expected completion Date : March 2019
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Foundation flooring and piling work has progressed to Floor 17.
-
Systems installation
Internal conduit installation underway on Floor 10.
-
Architectural Work
Bricklaying work underway on Floor 8 and Floor 3.