THE LINE Asoke-Ratchada
Expected completion Date : October 2018
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Structural work completed up to Floor 31
-
Systems installation
Installation of conduits completed up to Floor 28
-
Architectural Work
Brick-laying work and installation of exterior walls underway up to Floor 27