THE BASE Garden-Rama9
Expected completion Date : October 2018
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Structural flooring work underway up to Floor 36. Foundation flooring is completed.
-
Systems installation
Internal system installation work underway up to Floor 33
-
Architectural Work
Bricklaying and plastering work underway up to Floor 32