Date: November 2019
Date: November 2019
Date: November 2019
Date: November 2019
Date: October 2019
Date: October 2019
Date: October 2019
Date: October 2019
Date: September 2019
Date: September 2019
Date: September 2019
Date: September 2019
Date: August 2019
Date: August 2019
Date: August 2019
Date: August 2019

taka HAUS Ekamai 12

Expected completion Date : August 2019
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Foundation work completed on Tower A and B
  • Systems installation
    System installation underway on Floor 8 of Tower B
  • Architectural Work
    Bricklaying and plastering work underway on Zone 3 of Tower B