taka HAUS Ekamai 12

Expected completion Date : August 2019
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Structural work completed up to Floor 2 of Tower A
  • Systems installation
    System installations underway on Floor 1 of Tower A
  • Architectural Work
    Bricklaying and plastering work underway on Zone 3 of Tower B