THE BASE Garden-Rama9
Expected completion Date : October 2018
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Construction of water tank structure underway on deck level
-
Systems installation
A/C installation underway up to Floor 35
-
Architectural Work
Bricklaying and plastering work underway up to Floor 36