THE LINE Phahon - Pradipat
Expected completion Date : November 2019
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Concrete flooring work underway up to Floor 24
-
Systems installation
First Fix process implemented on units on Floor 12
-
Architectural Work
Installation of precast walls completed up to Floor 13