taka HAUS Ekamai 12
Expected completion Date : August 2019
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Construction of underground water tank system in Tower A and B all completed
-
Systems installation
Installation of systems underway up to Floor 3 of Tower A and Deck Level of Tower B
-
Architectural Work
Bricklaying and plastering work underway up to Floor 4 of Tower B