THE BASE Phetkasem

Expected completion Date : October 2019
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Construction of floors, piles and beams completed up to Floor 27
  • Systems installation
    Installation of in-wall conduits underway up to floor 15
  • Architectural Work
    Installation of piles underway up to Floor 18