taka HAUS Ekamai 12
Expected completion Date : August 2019
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Structural work is completed up to Floor 4 of Tower A
-
Systems installation
System installation work underway up to Floor 4 of Tower A
-
Architectural Work
Bricklaying and plastering work underway up to Floor 8 of Tower B