The Monument Thong Lo
Expected completion Date : May 2019
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Construction of the project's parking and swmming pool facilities all completed
-
Systems installation
Installation of electrical conduits underway on Floor 41
-
Architectural Work
Installation of aluminium frames underway on Floor 41