Date: January 2019
Date: January 2019
Date: January 2019
Date: January 2019
Date: December 2018
Date: December 2018
Date: December 2018
Date: December 2018
Date: November 2018
Date: November 2018
Date: November 2018
Date: November 2018
Date: October 2018
Date: October 2018
Date: October 2018
Date: October 2018


Expected completion Date : November 2019
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.

  • Structural Work
    Structural footing & flooring work completed up to Floor 23
  • Systems installation
    Structural flooring work underway up to Floor 26
  • Architectural Work
    Architectural work underway up to Floor 19