KHUN by yoo Inspired by Starck
Expected completion Date : November 2019
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Structural flooring work completed up to Floor 15
-
Systems installation
Installation of electrical and pumbling systems completed up to Floor 7
-
Architectural Work
Installation of precast materials completed up to Floor 6