Date: December 2019
Date: December 2019
Date: December 2019
Date: December 2019
Date: November 2019
Date: November 2019
Date: November 2019
Date: November 2019
Date: October 2019
Date: October 2019
Date: October 2019
Date: October 2019
Date: September 2019
Date: September 2019
Date: September 2019
Date: September 2019

THE LINE Phahon - Pradipat

Expected completion Date : November 2019
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Concrete flooring work underway up to Floor 35
  • Systems installation
    Installation of in-unit equipment underway on Floor 7
  • Architectural Work
    Installation of precast walls underway on Floor 21