Date: November 2019
Date: November 2019
Date: November 2019
Date: November 2019
Date: October 2019
Date: October 2019
Date: October 2019
Date: October 2019
Date: September 2019
Date: September 2019
Date: September 2019
Date: September 2019
Date: August 2019
Date: August 2019
Date: August 2019
Date: August 2019

THE BASE Phetkasem

Expected completion Date : October 2019
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Construction of the project's wells and roads underway
  • Systems installation
    Installation of sleeve materials and EE SAN FIRE AIR conduits underway up to floor 25
  • Architectural Work
    CM Wet Work underway on Floor 7