THE LINE Phahon - Pradipat

Expected completion Date : November 2019
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Concrete flooring work underway up to Floor 41
  • Systems installation
    Installation of end product materials underway on Floor 11
  • Architectural Work
    QC end product work underway on Floor 7