THE BASE Sukhumvit 50

Expected completion Date : December 2019
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Structural flooring work underway on Zone A1 and A2 on Floor 4 of Tower A
  • Systems installation
    Installation of sleeve and sanitation systems, electrical conduits and flloring work all underway on Floor 5
  • Architectural Work
    Installation of walls on Floor 2 of both Tower A and B