La Casita Hua Hin

Expected completion Date : November 2019
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Structural work is completed on Floor 3 of Tower A.
  • Systems installation
    Installation of electrical systems underway on Floor 2. Installation of pumbling systems underway on Floor 2. Installation of A/C systems underway on Floor 1.
  • Architectural Work
    Structural work is completed on Floor 2 of Tower A.