THE BASE Phetkasem
Expected completion Date : October 2019
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Structural work completed on Floor 30 (Deck Level)
-
Systems installation
Installation of electrical systems underway on Floor 28. Installation of pumbling systems underway on Floor 30. Installation of A/C systems underway on Floor 28.
-
Architectural Work
Wall construction is completed on Floor 30 and QC Control is underway.