THE BASE Central - Phuket

Expected completion Date : October 2019
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Structural work is underway for Tower C, up to Floor 7 for Zone 1 and Roof Level for Zone 2.
  • Systems installation
    Installation of electrical systems underway on Floor 3. 'Installation of pumbling systems underway on Floor 3. Installation of A/C systems underway on Floor 2 of Tower C.
  • Architectural Work
    Architectural work is not yet started for Tower C.