oka HAUS

Expected completion Date : February 2021
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Structural work completed on Floor 38.
  • Systems installation
    Installation of electrical systems underway on Floor 22.
    Installation of pumbling systems underway on Floor 22.
    Installation of A/C systems underway on Floor 15.
  • Architectural Work
    Wall construction is completed on Floor 27.