THE BASE Saphanmai

Expected completion Date : July 2020
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Structural work is completed on Floor 7.
  • Systems installation
    Installation of electrical systems underway on Floor 4.
    Installation of pumbling systems underway on Floor 4 .
  • Architectural Work