TIGER LANE

Expected completion Date : July 2019
  • A construction permit has already been issued.
  • Structural Work
    Structual work is completed
  • Systems installation
    Installation of electrical systems underway.
    Installation of pumbling systems underway.
    Installation of A/C systems underway.
  • Architectural Work
    Wall construction is completed and QC Control is completed.