La Casita Hua Hin

Expected completion Date : November 2019
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Structural work is completed on Floor 8 of Tower C.
  • Systems installation
    "Installation of electrical systems underway on Floor 5. 'Installation of pumbling systems underway on Floor 5. 'Installation of A/C systems underway on Floor 3 of Tower C."
  • Architectural Work
    Structural work is completed on Floor 5 of Tower C.