XT Huaikhwang

Expected completion Date : April 2021
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Structural work is completed on Floor 22.
  • Systems installation
    Installation of electrical systems underway on Floor 13.
    Installation of pumbling systems underway on Floor 13.
    Installation of A/C systems underway on Floor 12.
  • Architectural Work
    Wall construction is completed on Floor 11.