XT Phayathai

Expected completion Date : December 2022
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Structural work is completed on TOP FLOOR
  • Systems installation
    Installation of electrical systems underway on Floor 40.
    Installation of pumbling systems underway on Floor 40.
    Installation of A/C systems underway on Floor 40.
  • Architectural Work
    Architectural is completed on Floor 40.