PROJECT PROGRESS

EDGE Central Pattaya
Expected completion Date : October 2021
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Structural work completed on Deck Level
-
Systems installation
Installation of electrical systems underway on Floor 30.
Installation of pumbling systems underway on Floor 30.
Installation of A/C systems underway on Floor 30. -
Architectural Work
'Architectural is completed on Floor 30.