EDGE Central Pattaya

Expected completion Date : October 2021
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Structural flooring work completed on floor 27
  • Systems installation
    Installation of sleeve materials underway on floor 20.
  • Architectural Work
    Wall construction is completed on Floor1 4.