Date: March 2023
Date: March 2023
Date: March 2023
Date: March 2023
Date: February 2023
Date: February 2023
Date: February 2023
Date: February 2023
Date: January 2023
Date: January 2023
Date: January 2023
Date: January 2023
Date: December 2022
Date: December 2022
Date: December 2022
Date: December 2022

dcondo Panaa

Expected completion Date : June 2023
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Structural work completed Tower A Zone 100%
    Tower B on Rooftop 100%
  • Systems installation
    Eletric work on Floor 6 for Tower A,and on Floor 7 for Tower B
    Plumbling work on Floor 8 for Tower A, floor 8on Tower B
  • Architectural Work
    Installation precast and interior wall on Floor 8 and Tower B Completed 100%
    Texca wall work on floor 7 tower A and Floor 8 tower B.