PROJECT PROGRESS
SELECT PROJECT

Others project progress

The LINE Vibe
Expected completion Date : May 2024
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Structural work completed 100% on Floor 27
Construction work on Floor 25 60% and on floor 29 15% -
Systems installation
Installation eletric conduit 75% on Floor 27-28
Installation sleeve meterial completed on floor 27-28 75%
Air conditioning duct work 90% on Floor 18-19 -
Architectural Work
Brick work on floor 17 100%
Brick work and Tile work on Floor 18 70% and Floor 19 52%
Installation of door and window up tp 13-16 floor 70%