Date: March 2024
Date: March 2024
Date: March 2024
Date: March 2024
Date: February 2024
Date: February 2024
Date: February 2024
Date: February 2024
Date: January 2024
Date: January 2024
Date: January 2024
Date: January 2024
Date: December 2023
Date: December 2023
Date: December 2023
Date: December 2023

THE LINE Vibe

Expected completion Date : May 2024
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Pile-driving work all completed.
    Structual work is completed on Floor 33
  • Systems installation
    Installation of eletric work is completed on Floor33.
    Installation of pumbling systems underway on Floor 33.
    Installation of A/C systems underway on Floor 33.
  • Architectural Work
    Wall construction is completed on Floor 33 and QC Control is underway