PROJECT PROGRESS
valles HAUS
Expected completion Date: 19 Feb 2027
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Pile-driving work is completed 100%
Tower A: Structual work is finished up to 7th floor
Tower B: Structual work is finished up to 7th floor
Tower C: Structual work is finished up to 7 th floor -
Systems installation
Tower A: Installations of eletrical systems are finished up to 6 th floor
Tower A: Pumbling systems on 7 th floor
Tower A: A/C system up to 5 th floor
Tower B: Pumbling systems on 4 th floor
Tower C: Pumbling system on 4 th floor -
Architectural Work
Tower A: Wall construction is finished up to 6 th floor
Tower B: Wall construction is finished up to 4 th floor
Tower C: Wall construction is finished up to 4 th floor