Date: October 2026
Date: October 2026
Date: October 2026
Date: October 2026
Date: September 2026
Date: September 2026
Date: September 2026
Date: September 2026
Date: August 2026
Date: August 2026
Date: August 2026
Date: August 2026
Date: July 2026
Date: July 2026
Date: July 2026
Date: July 2026

valles HAUS

Expected completion Date: December 2026
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Pile-driving work is completed 100%
    Tower A:Structual work is finished up to 7 th floor
    Tower B:Structual work is finished up to 7 Floor
    Tower C:Structual work is finished up to 7 floor
    Tower D:Structual work is finished up to 2 nd floor
  • Systems installation
    Tower A: Installations of eletrical systems are finished up to 7th floor
    Tower A: Pumbling systems on 7 th floor
    Tower A:A/C system up to 7 th floor
    Tower B : Eletric system up to 7th floor
    Tower B: Pumbling systems on 7 th floor
    Tower B: A/C system are finished up to 7th floor
    Tower C: Eletrical system are finished up to 7 th floor
    Tower C: Pumbling system on 7 th floor
    Tower C: A/C system up to 7 floor
  • Architectural Work
    Tower A: Wall construction is finished up to 7 th floor
    Tower B: Wall construction is finished up to 7 th floor
    Tower C: Wall construction is finished up to 7 th floor
    In progress of QC End Product