valles HAUS
Expected completion Date: December 2026
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Pile-driving work is completed 100%
Tower A:Structual work is finished up to 7 th floor
Tower B:Structual work is finished up to 7 Floor
Tower C:Structual work is finished up to 7 floor
Tower D:Structual work is finished up to 2 nd floor -
Systems installation
Tower A: Installations of eletrical systems are finished up to 7th floor
Tower A: Pumbling systems on 7 th floor
Tower A:A/C system up to 7 th floor
Tower B : Eletric system up to 7th floor
Tower B: Pumbling systems on 7 th floor
Tower B: A/C system are finished up to 7th floor
Tower C: Eletrical system are finished up to 7 th floor
Tower C: Pumbling system on 7 th floor
Tower C: A/C system up to 7 floor -
Architectural Work
Tower A: Wall construction is finished up to 7 th floor
Tower B: Wall construction is finished up to 7 th floor
Tower C: Wall construction is finished up to 7 th floor
In progress of QC End Product