valles HAUS

Expected completion Date: February 2027
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Pile-driving work is completed 100%
    Tower A:Structual work is finished up to rooftop
    Tower B:Structual work is finished up rooftop
    Tower C:Structual work is finished up to rooftop
    Tower C:Structual work is finished up to 2 nd floor
  • Systems installation
    Tower A: Installations of eletrical systems are finished up to 7th floor
    Tower A: Pumbling systems on 7 th floor
    Tower A:A/C system up to 7 th floor
    Tower B : Eletric system up to 5 th floor
    Tower B: Pumbling systems on 5 th floor
    Tower B: A/C system are finished up to 5 th floor
    Tower C: Eletrical system are finished up to 6 th floor
    Tower C: Pumbling system on 6 th floor
    Tower C: A/C system up to 6 fl
  • Architectural Work
    Tower A'Wall construction is finished up to 7 th floor
    Tower B'Wall construction is finished up to 7 th floor
    Tower C'Wall construction is finished up to 7 th floor
    In progress of QC End Product