valles HAUS

Expected completion Date: 19 Feb 2027
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Pile-driving work is completed 100%
    Tower A: Structual work is finished up to 7th floor
    Tower B: Structual work is finished up to 7th floor
    Tower C: Structual work is finished up to 7 th floor
  • Systems installation
    Tower A: Installations of eletrical systems are finished up to 6 th floor
    Tower A: Pumbling systems on 7 th floor
    Tower A: A/C system up to 5 th floor
    Tower B: Pumbling systems on 4 th floor
    Tower C: Pumbling system on 4 th floor
  • Architectural Work
    Tower A: Wall construction is finished up to 6 th floor
    Tower B: Wall construction is finished up to 4 th floor
    Tower C: Wall construction is finished up to 4 th floor