dcondo Campus Resort Rangsit
Expected completion Date : December 2019
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Structural work completed on Deck Level of Tower A.
-
Systems installation
Installation of electrical systems underway on Floor 5.
Installation of pumbling systems underway on Floor 4.
Installation of A/C systems underway on Floor 6 of Tower A -
Architectural Work
Architectural work is completed on Floor 8 of Tower A