The concrete foundation has been completed.
Currently over 40% of structural work has already been completed. Concrete flooring work has been completed up to the 5th floor.
Visit our show units on Sukhumvit 77 today, open daily 09.00 – 18.00
To check available units, please call 1685


31 August, 2006
The progress of work on August 2006
A brand-new seaside condominium in heavenly Hua Hin. Here, you can make the most of your getaway time and do simply anything your heart desires.
31 July, 2006
The progress of work on July 2006
A brand-new seaside condominium in heavenly Hua Hin. Here, you can make the most of your getaway time and do simply anything your heart desires.
31 July, 2006
The progress of work on July 2006
A brand-new seaside condominium in heavenly Hua Hin. Here, you can make the most of your getaway time and do simply anything your heart desires.
31 August, 2006
The progress of work on August 2006
A brand-new seaside condominium in heavenly Hua Hin. Here, you can make the most of your getaway time and do simply anything your heart desires.