THE LINE Asoke-Ratchada

Expected completion Date:March 2019
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Structural flooring and piling works have completed up to Floor 5
  • Systems installation
    Installation of electrical conduits on Floor 8
  • Architectural Work
    Brick-laying work underway on Floor 2