SHUSH Ratchathewi

Expected completion Date: September 2026
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Pile-driving work is finished 100%
    Structure work is finished up to Rooftop
  • Systems installation
    Installation of electrial systems is finished up to 29 th floor
    Installation of pumblingl systems is finished up to 29th floor
    Installation of A/C systems is finished up to 29th floor
  • Architectural Work
    Wall Constuction is finished up to 31 th floor
    In progress of QC End Product