PROJECT PROGRESS
THE BASE Wongsawang
Expected completion Date: 30 JUN 2027
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Pile-driving work is completed 100%
Structual work is finished up to 27th floor -
Systems installation
Installations of eletrical systems are finished up to 1st floor, pumbling systems on 1st floor
-
Architectural Work
Wall construction is finished up to 12th floor